|
Other
Issues / Archive - Metro
Rail
Metro
Rail
Background
| Articles and Statements
Statements
and Letters
September
19, 1994
The Honorable
Federico F. Pena
Secretary
Department of Transportation
400 Seventh Street, S.W.
Washington, D.C. 20590
Dear Secretary
Pena:
For more than
a year, the Los Angeles Times has published a series of investigative
reports on problems regarding construction of the Metro Rail Red
Line in Los Angeles. They are serious problems, including the presence
of methane gas and hydrogen sulfide in some stations, tunnel walls
that were built much thinner than contract specifications, and ground
sinkage along Hollywood Boulevard of up to nine inches.
At the core
of these failures is a pattern of what appears to be indifference
to accepted construction practices and disregard of existing requirements.
I request that the Department of Transportation conduct a formal
review of these problems -- including the performance of the Metropolitan
Transit Authority (MTA), its subway construction contractors, and
its management firm -- to determine what federal action is appropriate
under the circumstances.
The following
cases demonstrate why a comprehensive review is warranted.
METHANE GAS
AND HYDROGEN SULFIDE LEAKS
In 1985, I raised
concerns about constructing and operating a subway system in areas
where dangerous gas is present after a large methane gas explosion
occurred in my district. The City Council appointed a committee
of technical experts to address my concerns, and transit officials
promised to implement its list of recommendations. It ignored at
least two: that gas sensors be put in passenger areas at the platform
level inside the stations and in elevated exhaust ducts outside
the station, and that automated emergency fans be used to disperse
unacceptable levels of gas. Instead, according to a Los Angeles
Times story on May 23, 1994, sensors were placed only in exhaust
ducts outside the station at almost street level, and the emergency
fans remained manually operated. Hydrogen sulfide is heavier than
air, and placement of sensors inside the stations at passenger platform
levels was considered necessary to get adequate readings of the
presence of the gas.
To prevent dangerous
gases from penetrating tunnel walls, transit officials spent an
additional $16 million to seal the tunnels with a high-density polyethylene
liner. In 1987, before construction began, analysts hired by the
U.S. Department of Transportation indicated to transit officials
the importance of installing this lining properly. According to
the Los Angeles Times, however, the plastic liner was "routinely"
punctured and not always repaired. In fact, a chief inspector reported
that the contractor intentionally violated proper procedures and
refused to allow workers to patch holes. During construction, a
private testing lab, Smith-Emery Co., found "widespread deficiencies."
Moreover, an outside consulting firm hired by the MTA concluded
that the management firm failed to adhere to "acceptable industry
practice."
SUBWAY WALL
DEFECTS
The Los Angeles
Times reported in August and September, 1993 that the subway walls
in dozens of areas in the 1.9 mile Red Line segment from Union Station
to Pershing Square were built thinner than the contract specifications
required. More than 2,000 feet (twenty-one percent) of the tunnel
walls were reported to be only six to eight inches thick instead
of the required twelve inches. The problem was attributed to tunneling
misalignment.
Inspectors are
required to inspect concrete forms before contractors can pour concrete.
According to reports, on at least a dozen occasions the contractor
poured concrete when the inspector had withheld authorization to
do so.
A tunnel designer
warned transit officials in late 1992 that areas with thin walls
could fail to hold in an earthquake or under other stresses. Transit
officials subsequently required the contractor to reinforce the
tunnel with steel plates to cover ninety feet in three locations.
Transit officials maintained that the walls were structurally sound
and nothing more was needed.
Outside experts
indicated that steel reinforcing rods would also need to be used.
The contractor claimed to have put rods in about 300 feet of the
tunnel in addition to steel plates in the three locations. The Los
Angeles Times reported in a later story, however, that steel plates
had only been installed to cover forty feet in two locations, and
that MTA did not know how much of the tunnel contained the reinforcing
rods.
Independent
outside specialists hired by the MTA to investigate concluded that
"deviations from written procedures are at variance with what
is considered acceptable industry practice."
GROUND SINKAGE
The contract
specifications for the Vermont Avenue and Hollywood Boulevard tunnels
required the contractor to perform contact grouting. The contractor
proposed eliminating the grouting requirement, and the MTA did not
enforce it. After the ground sank, the MTA stated that it had wanted
to save the $1 million the grouting would have cost. Instead, the
$165 million contract is expected to wind up costing $200 million.
An MTA tunnel
expert warned in October 1993 that the specification for contact
grouting needed to be enforced because he saw evidence of "irregular
ground subsidence" on Vermont Avenue. His superiors did not
accept his recommendation. The MTA did begin to require contact
grouting in March 1994 after 1/3 of the tunneling had been completed.
By July 27,1994,
the MTA reported that the sinkage on Hollywood Boulevard measured
about four inches. On August 3, 8, 9, and 10 nonconformance reports
were filed citing the contractor for failing to comply with the
grouting specification. On August 18, the MTA stopped tunneling,
and on August 20, the MTA reported that up to nine inches had sunk
along a nine-block area on Hollywood Boulevard.
On September
1, MTA's Tunnel Review Board report recommended that the contractor
begin compaction grouting to minimize further settlement. MTA's
chief design engineer, who drafted this report, had rejected a staff
engineer's recommendation in late July or early August to use compaction
grouting.
We have an obligation
to the public to ensure, at a minimum, that Metro Rail is constructed
according to acceptable industry practice, that contract specifications
are respected and enforced, that expert recommendations are followed,
and that the safety of the riding public is valued and guaranteed.
I appreciate your review of this matter and look forward to working
with you to determine how we should proceed.
With kind regards,
I am
Sincerely,
HENRY A. WAXMAN
Member of Congress
|